East Anglia THREE, UK

Complete solution of 320 kV onshore and offshore cables system with a capacity of 1 400 MW.

Key Facts

Client:

ScottishPower Renewable (SPR)

Location of the project:

The North Sea

Quantity of order:

Complete solution of 320 kV onshore and offshore cables system with a capacity of up to 1 400 MW.

Total route length:

2 x 147 km of onshore and 2 x 37 km of offshore cable

Duration:

2023-2026

Scope

cable closeup
High voltage cable onshore installation in Trelleborg
New factory Karlskrona 2027
East Anglia THREE
East Anglia THREE

The project

The East Anglia THREE need reliable high-voltage power links.

East Anglia three web image_26 aug-01 draft 04-01.jpg

The solution

NKT manufacture all cable systems needed and install them using our cable-laying vessel NKT Victoria.

This milestone in among the largest windfarms in the world, marks the point where offshore meets onshore - It is where engineering excellence, environmental responsibility, and business execution converge to enable the delivery of clean, renewable energy to the grid. This achievement reflects the dedication of our teams, partners, customers and stakeholders.
East Anglia three

East Anglia THREE could power up to 1.3 million homes