Supply contract for 320 kV offshore and onshore HVDC system and 400 kV AC onshore cable
Total cable length
Total cable length produced: approx. 674 km offshore cable and 212 km onshore cable + 23 km onshore HVAC cable
Total cable route length
170 km 320 kV DC offshore cable, 50 km 320 kV DC onshore cable as well as 1,2 km route of 400 kV AC onshore cable.
Duration
2023-2027
Scope
The project
NKT contributes to one of the world´s largest offshore wind zones
We have now delivered the final HVDC onshore cable drum for the impressive Hornsea 3 Offshore Wind Farm. Thanks to the Ørsted Hornsea 3 project team for good collaborative working.