Troll C West

Troll West, Norway

Electrifications of platforms in The North Sea

Key facts:

Client

Equinor Energy AS, Petoro AS, A/S norske Shell, TotalEnergies EP Norge and ConocoPhillips Skandinavia AS

Location of the project

The North Sea

Quantity of the order

145 kV high-voltage AC offshore power cable system with a capacity that goes up to 150 MW

Total cable route length

85 km and 20 km

Duration

2020-2025

Scope

The project

Power from shore connects to the national grid at Kollsnes