The study was performed at a construction site in Copenhagen –a conversion of a former office and production building into a hotel.
Transport times have been measured on a Qaddy and a wooden cable drum with 500 meters of 3G 1.5 mm2 cable. Furthermore, an unwinder for the wooden cable drum was applied.
- 1st chronometry was performed on a transport from the container to the working site inside the building
- 2nd chronometry was performed on a transport between 5 different rooms inside the building
The results speak for themselves
(1st) The time saved with Qaddy= 60% compared to a wooden cable drum, so transport on Qaddy to the installation site inside the building is 3 times faster!
(2nd) Time saved with Qaddy= 45% compared to a wooden cable drum so transport on Qaddy inside the building is twice as fast!
On top of that, employees achieve an improved physical working environment, because they avoid heavy lifting and back twists.
Take a look at the study below and learn more.